2021 - 2022
Chemical Plant Demolition
Priestly Demolition was contracted to demolish 3 buildings in Haverhill, Ohio. Our engineering team created a step by step plan to successfully demolish each of these structures safely. Starting with the smallest of the 3 buildings, PDI’s team used a method called “tripping” to selectively cut the taller structures down so that they fell in a controlled manner and in the proper direction. The materials from this project were sorted, processed, and then loaded onto rail cars and transported to recycling facilities.
Key challenges:
- Cold weather
- Chemicals manufactured onsite
- Shipping recycled material by rail
- Height of structures to demolition in correlation to structures remaining